Design and implementation of connections to support the supply of main lines in Muzdalifah and Makkah

Project Objectives and Linking Them to Strategic Objectives

Strategic Objective:

Supporting the work of some water networks in Muzdalifah, Arafat, and Makkah al-Mukarramah

Strategic Performance Indicator:

Completion of the project and its utilization before the Hajj season of 1445 AH

Project Objectives

Implementing a new inlet for the 10,000-gallon tank in Muzdalifah from the existing 900mm diameter line
Implementing a network between the new 10,000-gallon tank inlet and the 500mm and 300mm lines in Muzdalifah
Constructing valve chambers on the 300mm Muzdalifah reciprocating line
Implementing a feeder line connecting the 500mm and 1600mm lines in Muzdalifah
Recycling water from the Martyrs' Tanks by connecting the Martyrs' Tanks' outlet to the 600mm Umrah line and the 600mm second ring road
Utilizing the Al-Maghmas Complex to support water supply to Mina and the central area of ​​Makkah al-Mukarramah by making connections on the 1400mm line from Al-Jurainah
Project Scope

Implementing water lines Main and network pipes with diameters ranging from 300 to 1000 mm, totaling 2,400 meters in length, in Muzdalifah, Arafat, and Makkah, including valves, valve chambers, and connection works to existing lines.

Bright – A leader in implementing infrastructure projects to serve the holy sites efficiently and reliably.

Additional Info

  • Contracting Projects - Infrastructure
  • OwnerElectrical City
  • Project Duration520 Day
  • Project StatusExecuted